1 ) Progress
– Permits, insurance and guarantees: 100% completed
– Temporary Field Facilities: 80% completed
– Measurement / Field layout : 100% completed
– Cleaning, grubbing and gradings: 20% completed
– Trimming, removal and occasional cutting trees: 100% completed
2 ) Tasks completed:
– Truck delivered aggregates for the path of the chakras
– Quotations by the subcontractor in electricity
– Site inspection by ACO with MCL and Orlando to discuss the natural rocks and drainage channels and systems
– Mobilization of additional labour
– Mobilization of equipment in the field, including steel required for the Pyramid and the toilets / showers
– ACO informs MCL the need to test the equipment before use and reminds MCL the obligation to undertake technical validation of all equipment.
– A bulldozer is at work on site to clear and grade the site of the Pyramid and the road
Rapport d’étape No 02 – Défrichement
Du 18 au 21 mai 2011
1) avancements des travaux :
– Permis, assurances et garanties = 100 %
– Installations temporaires = 80%
– Mesurage / configuration du terrain = 100%
– Nettoyage, arrachage et nivellement du terrain = variable ±20%
– Coupe des arbres = 100%
2) Travaux accomnplis
– Déchargement de camions d’agrégats pour le sentier des chakras
– Cotation à venir par le sous-contractant en électricité
– Inspection du site par ACO avec MCL et Orlando : discussions sur les rochers et canaux de drainage à effectuer
– Mobilisation de main d’œuvre additionnelle
– Mobilisation de l’équipement sur le terrain, dont l’acier requis pour la Pyramide et les toilettes/douches
– ACO mentionne à MCL la nécessité de tester le matériel d’agrégats avant son utilisation pour le remplissage requis. ACO rappelle à MCL l’obligation de procéder à la validation technique de tout matériel avant son utilisation.
– Un bulldozer est en action sur place pour dégager et niveler le site de la Pyramide et la route