Chakras Trail and Stations
1. Final tapping and clearing works along the chakras station 1-7 slabs still on-going including backfilling works along the chakras stations trials.
2. Maintenance of open earth canal drainage system on going. (more…)
Chakras Trail and Stations
1. Partial trimming, backfilling and compacting works along the chakras stations 1-7 trail still on going.
2. Maintenance of open earth canal drainage system on going.
3. Clearing and partial backfilling works along the chakras stations 1 to 7 are ongoing
4. Maintenance of drainage open earth canal along the chakras area and below the chakras area still on going.. (more…)
Special music composition by Jan Frank / Speciální hudební kompozice Jan Frank za Pyramida světla
To listen to this beautiful music track, click on this video:
Although John Frank will be busy in November and thus will not attend the inauguration, we asked for his feedback in an interview. (more…)
Chakra Trail and Stations
1. Gravel bedding and concreting of slabs with double bamboo reinforcements along the chakras stations 2, 3 & 7 all completed.
2. Partial trimming and backfilling works along the chakra trail ongoing.
3. Re-doing of chakra station 1 to 2 still ongoing.
4. Maintenance of open earth canal drainage system ongoing. (more…)
Progress report Nr 17: August 29 – September 03, 2011 (english,français,deutsch;español)
Chakras Stations
1. Gravel bedding and compacting at chakras station 7 slab on going
2. Fabrication of double bamboo reinforcements for chakras stations 2, 3 & 7 on going
3. Maintenance of drainage open earth canal along the chakras area on going.
4. Gravel bedding and trimming works along the chakras station 7 completed, including installation of first layer bamboo reinforcements also completed, ready for concreting.
5. Removal of concreted beams at chakras stations 2 & 3 completed. Partial gravel surfacing and compacting works on going.
6. Gravel surfacing and compacting along the chakras station2 including installation of bamboo reinforcement first layer completed.. (more…)
Chakras
1. Concreting of slab of chakras stations 4 and 6 completed.
2. Gravel bedding and compacting of chakras station 7 on-going.
3. Demolition of concreted tie-beams at chakras station 2 completed while that of chakras stations 2 & 3 are still on-going.
4. Fabrication of bamboo reinforcement for chakras stations 2, 3 & 7 on going. (more…)